Fuselage September 2006 Updates
September 1, 2006 Reamer is in - 2.0 hrs
September 2, 2006 Gear Weldments & Flap Motor Enclosure - 3.0 hrs
September 3, 2006 Baggage area parts & Leftside Canopy Decks - 7.0 hrs
September 4, 2006 Baggage area & Rightside Canopy Decks - 7.0 hrs
September 6, 2006 Baggage Area and Flap Motor - 3.0 hrs
September 7, 2006 Flap motor assembly and G Weldment sealing - 2.0 hrs
September 9, 2006 Flap motor & Top Skins - 5.0 hrs
September 10, 2006 Baggage Bulkhead - 5.0 hrs
September 11, 2006 Baggage Bulkhead Nutplates - 2.0 hrs
September 13, 2006 F-6111 Stiffeners - 1.0 hrs
September 20, 2006 Fuel Pump & Forward Fuse - 2.0 hrs
September 23, 2006 High Pressure Fuel Pump - 4.0 hrs
September 24, 2006 High Pressure Fuel Pump - 3.0 hrs
September 27, 2006 High Pressure Fuel Pump - 2.0 hrs
September 28, 2006 Floor Rib Fix - 2.0 hrs
September 30, 2006 Fuel Pump Enclosure - 2.0 hrs

This website was built to document my work in compliance with the FAA requirements needed to certify my aircraft.
My experiences and comments are by no means to be considered as instructions on how to build any aircraft.