Fuselage March 2007 Updates
March 01, 2007
Strobe Wiring - 2.0 hrs
March 03, 2007
Strobe Wiring & Aileron Trim - 4.0 hrs
March 04, 2007
Flap Motor and Forward Panel - 4.0 hrs
March 11, 2007
More Fab and Rollbar Fitting - 4.0 hrs
March 12, 2007
Canopy Frame Fitting - 2.0 hrs
March 13, 2007
Canopy Frame Fitting - 2.0 hrs
March 15, 2007
Right Armrest stiffener - 2.0 hrs
March 16, 2007
Canopy Roll Bar - 3.0 hrs
March 17, 2007
Wharton Flyin - 0.0 hrs
March 17, 2007
Wharton Flyin - 0.0 hrs
March 25, 2007
Misc Stuff - 8.0 hrs
March 30, 2007
More Canopy Frame Work - 5.0 hrs
March 31, 2007
Canopy Slider Bracket - 1.0 hrs
This website was built to document my work in compliance with the FAA requirements
needed to certify my aircraft. My experiences and comments are by no means to be
considered as instructions on how to build any aircraft.
|
| |