Finish Kit August 2012 Updates
August 02, 2012
The Last Rivets!...... - 1.0 hrs
August 03, 2012
Weight and Balance Complete...... - 4.0 hrs
August 04, 2012
Completed Canopy Preping for Inspection...... - 5.0 hrs
August 08, 2012
Preping for Inspection...... - 2.0 hrs
August 10, 2012
Preping for Inspection...... - 7.0 hrs
August 11, 2012
The Inspection...... - 8.0 hrs
August 12, 2012
Putting the Bird back together...... - 6.0 hrs
August 16, 2012
Putting the Bird back together...... - 2.0 hrs
August 18, 2012
Reskinning the Right Elevator...... - 10.0 hrs
August 19, 2012
It's Official N754RV is a real plane...... - 7.0 hrs
August 22, 2012
Final Prep for First Flight...... - 3.0 hrs
August 23, 2012
First Flight is Here...... - 3.0 hrs
August 24, 2012
Second Flight...... - 0.0 hrs
August 28, 2012
Third Flight...... - 0.0 hrs
This website was built to document my work in compliance with the FAA requirements
needed to certify my aircraft. My experiences and comments are by no means to be
considered as instructions on how to build any aircraft.
|
| |