Fuselage September 2005 Updates
September 6, 2005
Parts Fabrication - Seats - 3.0 hrs
September 7, 2005
Parts Fabrication - Seats - 2.0 hrs
September 8, 2005
Parts Fabrication - Seats - 3.0 hrs
September 9, 2005
Parts Fabrication - Seats - 2.0 hrs
September 11, 2005
Parts Fabrication - Seats - 5.5 hrs
September 13, 2005
Priming Seat Parts - 2.0 hrs
September 23, 2005
Building Stopped - preparing for Hurricane Rita - 0.0 hrs
September 24, 2005
Houston Dodged a bullet - 0.0 hrs
September 25, 2005
Seat Backs - 2.0 hrs
September 26, 2005
Seat Backs - 1.0 hrs
September 28, 2005
Seat Backs - 2.0 hrs
September 29, 2005
Seat Hinges - 1.0 hrs
This website was built to document my work in compliance with the FAA requirements
needed to certify my aircraft. My experiences and comments are by no means to be
considered as instructions on how to build any aircraft.
|
| |