May 23, 2008
Mixture Bellcrank Finally.... - 4.0 hrs
Several nights this week I worked on the bellcrank bracket. I used JB Weld and it took several applications and it had to dry between each one. Then I had to prime it and paint with heat resistant flat black.
Today I installed it and its working perfect. Next I used a greenlee punch to cut the hole for the eyeball passthru for the mixture cable. Installed the cable and tested the throws from stop to stop.
Next I drilled out the eyeball for the throttle and installed it as well. All cables are installed and working correctly.
This website was built to document my work in compliance with the FAA requirements
needed to certify my aircraft. My experiences and comments are by no means to be
considered as instructions on how to build any aircraft.
|
| |